Thank you for visiting
East Link Consulting Group Website.

Following the strategic changes implemented to the business, as announced by our Managing Director Mr. Nigel N. Stanley, the East Link Group of companies will be operating under new management from 1st July 2019.

The main service streams will now be offered to our clients by an existing established entity PMCC Actus Sdn Bhd, strengthened by the injection of former ELC resources.

Revised contact details are now as follows:

Jamie Duncan – Director

Mobile: +60 19 277 6892

Email: jamie@pmcc-corporation.com

PMCC Actus Sdn Bhd

Unit 611, 6th Floor, Block C,
Pusat Perdagangan Phileo Damansara 1,
Jalan Damansara,
46350 Petaling Jaya,
Selangor, Malaysia

Phone: +603 7620 6136

Website: www.pmcc-corporation.com

For all matters related to ELC Rail Sdn Bhd – please revert to

Jeff Hewitt – Managing Director

Mobile: +60 12 296 0262

Email: jeff.hewitt@elcrail.com

Leighton Contractors Philippines Inc – Therma South Power Station

02 Apr 2013

On 2nd April East Link Consulting were awarded a commission to provide procurement services to Leighton Contractors Philippines Inc on their Therma South Power Station Project. The Project consists of the design, engineering, procurement, construction, installation and commissioning of the Power Facility on a site spanning the boundary of Davao City and Sta. Cruz, Davao del Sur in the Philippines.

In summary the Project involves:

  • 2-150 Megawatt circulating fluidized-bed (CFB) coal-fired power plant being developed for Therma South Inc. a wholly owned subsidiary of Aboitiz Power Corporation.
  • The Project is designed to address the Mindanao region’s power supply needs.
  • 120 meter diameter coal storage dome
  • Coal conveyors
  • Ship unloader and stacker reclaimer
  • 1,500m of 2.5 meter diameter circulating water mains
  • Circulating water intake structure
  • Project wide piling
  • Site infrastructure
  • Ash lagoons
  • Power island
  • Coal unloading jetty
  • Temporary unloading jetty 
  • Site wide ancillary buildings.
  • The Project shall be delivered by the consortium project team of Leighton Contractors (Philippines), Inc. (“LCPI”) and Black and Veatch International (“BVI”).

 

East Link Consulting are providing procurement services in terms of both strategy and execution.